HEP – SINGIDA

Project: HEP – SINGIDA

Title:

Description:

HEP – SINGIDA

  • World Bank
  • TANZANIAN government

1.⁠ ⁠Overview of the project
TR198/2024/2025/W/02 will be executed in all districts of Singida region, which are Singida DC, Ikungi, Manyoni, Mkalama and Iramba. The project aims to provide electricity to 120 Hamlets and connect 3960 initial-Customers in all 8 Constituencies of Singida Region meaning that 15 Hamlets in every Constituency shall be electrified.

The duration of the project is 730 days equivalent to Twenty-four (24) months from 10th May, 2025.
The scope of work for Lot 1 in the original contract consists of LV 240 km, 119 transformers of 33/0.4KV, 100kVA, One Transformer of 11/0.4KV, 100KVA 3600 single-phase customers, and 360 three-phase customers.